## Why Fraction Addition Slows You Down
In school, everyone learns the reciprocal rate formula for combined work:
$$\frac{1}{T} = \frac{1}{A} + \frac{1}{B} + \frac{1}{C}$$

While algebraically correct, adding fractions with denominators like 12, 18, and 24 under a 2-minute time limit invites arithmetic errors and wastes valuable scratchpad space.

The **LCM Unit Method** eliminates fractions entirely.

---

### The 3-Step LCM Method

#### Step 1: Assign a Convenient "Total Work" Value
Find the Least Common Multiple (LCM) of the given time values and assign it as the total number of "work units."

* *Example:* Pump A fills a tank in 12 hours. Pump B fills it in 18 hours. Pump C empties it in 24 hours.
* $\text{LCM}(12, 18, 24) = 72 \text{ units}$.

#### Step 2: Compute Integer Rates per Hour
* Pump A rate $= \frac{72}{12} = +6 \text{ units/hr}$
* Pump B rate $= \frac{72}{18} = +4 \text{ units/hr}$
* Pump C rate $= \frac{72}{24} = -3 \text{ units/hr}$ (Negative because it empties)

#### Step 3: Combine Rates with Clean Addition
$$\text{Net Combined Rate} = 6 + 4 - 3 = 7 \text{ units/hr}$$
$$\text{Time to fill tank} = \frac{\text{Total Units}}{\text{Net Rate}} = \frac{72}{7} = 10\frac{2}{7} \text{ hours}$$

---

### Handling "Alternating Work" and "Early Departure"
* If Worker A works alone for 3 hours before Worker B joins:
* Calculate work done by A: $3 \times 6 = 18 \text{ units}$.
* Calculate remaining work: $72 - 18 = 54 \text{ units}$.
* Time for A and B combined: $\frac{54}{6 + 4} = \frac{54}{10} = 5.4 \text{ hours}$.
* No fractions, zero common denominator calculations, 100% speed.